Tuesday, July 31, 2007

Growing Up Fast



After just one day, the first floor is almost there.

Sunday, July 29, 2007

Framing Began




Basement Slab Poured




The hole in the center is for the elevator shaft.

Drainage


Drainage pipes are installed under the gravel to drain water away from the foundation into a bucket in the corner. Sump-pump will pump water to the outside.

Sunday, July 22, 2007

Back-filled



After the backfill, it feels like a new house now.

Sunday, July 15, 2007

Waterproofing




To keep the basement dry, waterproofing is done as shown. The stadard is to have a coat of tar on the outside wall. We did something additional - on top on the tar, we applied UTC spray foam, at additional cost of $1.1/per sqf - for the peace of mind. Cost to clean a flooded basement runs tens of thousands so it is not a bad investment. The basement should be bone-dry.

Friday, July 13, 2007

Here is the foundation


Forms are removed after just one day.

Thursday, July 12, 2007

All done after a long day


Build a foundation - part 2






Forms were set and cement are ready to be poured. Here comes the cement truck. The two men crew worked hard to build the basement walls.

Monday, July 9, 2007

Saturday, July 7, 2007

Construction finally started


Construction crew dug a hole in the ground.
This is going to be the foundation.

Friday, July 6, 2007

Get a building permit

As our builder told us earlier on, building the house is the easy part - the hard part is to get the building permit. That is so true. We started the process at the beginning of the year. Finally, on June 27th, we got the building permit from the town.

Here is what is required for building permit application:

1. A recent certified plot plan less than 10 years of age.

2. Four sets of complete drawing of floor plans, professional architect or engineer's signed copy of contruction drawings.

3. Health Department approval for the septic system;

4. Conservation approval;

5. A zoning permit.

Since our plot plan is older, we had to re-survey the land. This is relatively easy - it took just a few days. Health Department tests can only be done in certain period and one needs to make appointment with them earlier on. Also our old house was built in the 50s, the age is shy of the limit. If it is over 60 years old, we need to go through the historical society, which can held up the building permit process for 2 months.

The most time consuming part is working with the architect to come up with a floor plan and get zoning approval. This is a long story and I will get into details later on. It took us several months and at the end we are just happy that it is over.

Thursday, July 5, 2007

Old House - It is gone.

The old house was knocked down on May14th, 2007. Now the journey begins ...


Building my own house

We decided to build our own house this year. Everyone is telling us that this is going to be quite an ordeal - it could be the best of the times, or the worst. No matter what, it is something worth remembering. So I created this blog to show the progress and share my experience. Enjoy.